Kilbourn Reservoir Park Project Update January 25, 2007

 

Kilbourn Reservoir Park Project Update
Jan. 17, 2007 - Jan. 25, 2007


A crew continues to demolish the western interior wall, interior support columns, and the concrete cap of the reservoir. The concrete is then stripped of metal and rebar and will be reused as backfill, along with soil that had been removed prior to demolition. The southwestern interior wall remains.

Demolishing the west interior wall, concrete cap and columns (Jan. 17, 2007)


Demolishing the west interior wall, concrete cap and columns (Jan. 17, 2007)


Reworking the crushed concrete to remove metal and rebar material (Jan. 17, 2007)  


Demolishing the west interior wall (Jan. 17, 2007)


The remaining section of the concrete cap and columns to be demolished (Jan. 17, 2007)